알래스카에서 자원개발하는 건 아직은 쉽진 않아보인다. 

 

 

https://www.mining.com/ambler-road-decision-now-expected-by-end-of-2024/

 

The Department of Interior (DOI) of the US has once again delayed the release of the record of decision (RoD) for the Ambler road project, which will give access to untouched deposits of copper, zinc, lead, silver and gold in north-western Alaska.

The resolution on Trilogy Metals’ (TSX, NYSE: TMQ) and South32’s (ASX, LON, JSE: S32) proposed 340-km (211-mile) road from the Upper Kobuk Mineral Projects (UKMP) to the Dalton Highway is now expected on the second quarter of 2024.

As of last week’s status report, the DOI was promising a decision by the end of the year.

The need for an industrial access road has been recognized by US lawmakers for decades, but it wasn’t until 2020 that the Bureau of Land Management (BLM) the Army Corps of Engineers, and the National Park Service issued a joint decision providing the federal authorizations needed to build it.

Last year, however, BLM suspended the permits issued under the Trump administration, citing a lack of adequate consultation with Alaska tribes and evaluation of the road potential impacts on fish and caribou habitats. 

 

The Biden administration suspended at the time the issuing of permits for all projects that cross federal lands. The Ambler access road would cut through gates of the Arctic National Park and Preserve, crossing 11 major rivers and thousands of streams.

Ambler Metals, formed in 2019 by Trilogy Metals and South32, said the new “unnecessary” delay threatened a project that will provide much-needed jobs and economic growth for Alaskans.

“We are obviously disappointed to hear the latest status update from the DOI,” president and CEO Ramzi Fawaz said in the statement.

“It has been a year since the court granted DOI’s request for a voluntary remand of the permit, providing ample time for the department to conduct the needed supplemental work on the EIS”, Fawaz added.

The UKMP projects, consisting on Arctic and earlier-stage Bornite copper assets, have a combined resource of 8 billion pounds of copper, 3 billion pounds of zinc and 1 million ounces of gold equivalent.